Structural Progress: The final steel decks for roofing are being installed, and the final concrete pour is being prepped for completion in early March. Remaining steel detailing will be completed in March.
Façade Progress: Insulation and brick are being installed in several areas including the North façade and courtyard. The overall South façade of the building has been completed. Exterior Framing, Air Barrier and metal panels are progressing on the South Face of Area C, D and Courtyard.
Interior Progress: The South portion has been closed in drywall and paint is in progress. In the North building, the Levels 1 and 2 of the West wings are being inspected and closed in with drywall while multiple levels of the East wings of the building have Mechanical, Electrical, Plumbing, and Sprinkler rough-ins progressing through installed framing.
Utility Progress: Structure installations are continuing with large Sand Filter and Underground Stormwater Treatment structures being excavated, set by crane, and backfilled.
Sitework: The South side of the site is being graded in preparation for curb and gutter installation in early March.
January 2026
Structural Progress: The final steel decks for roofing are being installed, and the final concrete pour has been scheduled. Stairwells are also being installed to allow for full enclosure of the building.
Façade Progress: Insulation and brick are being installed in several areas including the main entrance façade and portions of the courtyard. The overall South façade of the building has been completed, and the Dancing People feature has been re-installed.
Interior Progress: The South portion of the building passed Wall Close-In inspections and drywall hanging has begun. CMU walls are getting their first few coats of paint. In the North building, the West wings are finishing wall rough-ins in preparation for Wall Close-In inspections and drywall installation while the East wings of the building have Mechanical, Electrical, Plumbing, and Sprinkler rough-ins progressing through newly installed framing.
Utility Progress: Structure installations are continuing with large Sand Filter and Underground Stormwater Treatment structures being excavated, set by crane, and backfilled.
Sitework: The Bus Loop received it’s first layer of asphalt and is now fully intact.
December 2025:
Structural & Exterior Progress: The building’s steel frame has reached its highest point in new sections, and roof installation is expanding across the site to seal the building from the elements.
Facade & Finishing Touches: Modern metal panels and brickwork are now being installed on several exterior walls, including the inner courtyard areas.
Interior Preparation: Major progress was made on the "bones" of the building, with fireproofing applied to the lower levels and interior wall framing now underway.
Utility & Pipe Work: Crews are heavily focused on "roughing-in" the mechanical, electrical, and plumbing systems (the hidden wiring and pipes) across most of the facility.
Roads & Fields: The bus loop is taking shape with new concrete curbs and gutters installed, while the ground is being leveled and prepared for the first layer of asphalt paving.
November 2025:
Building Framework Milestones: The structural steel and concrete floors are now finished in the first section of the building, while the steel frame for the third floor is successfully in place in other areas.
Exterior Weatherproofing: Workers have completed the roof and window installations for a large portion of the site, and the brick exterior on the west side is nearly finished.
Interior Utilities & Systems: Major electrical equipment has been delivered and installed, and crews have begun running the necessary mechanical piping throughout the building.
Interior Finishing: Painting has officially begun in the "back of house" service rooms, marking a transition toward interior completion.
Site Drainage & Infrastructure: Significant underground work was completed, including the installation and water-testing of large storm-water management structures and over 300 feet of new drainage piping under the athletic fields.
Northwood Project Schedule
Spring 2019: Design commencement
Fall 2023: Northwood students and staff relocate to holding facility
Fall 2024: Construction begins at Northwood HS
Fall 2027: Northwood students and staff move-in to new facility