Construction is scheduled to be completed for the re-opening of school for the 2017 - 2018 school year.

Update April 2016:

Visit this link to see photos of the demolition.

Take a look at the architectural plans for our new building designed by Moseley Architects.

 

Update November 2015: 

Wayside's facility is now scheduled to be modernized with a proposed completion date of August 2017.  Staff and students will move to a holding facility (Grosvenor Center) in January 2016.

  

Update November 2014: 

"The County Council adopted the FY 2016 Capital Budget and Amendments to the FY 2015-2020 Capital Improvements Program (CIP) on Nov. 17 2014.  Our modernization schedule has been revised with the Superintendent's Recommended FY2016 Capital Budget. Wayside will undergo a complete revitalization/expansion beginning in January 2016. Wayside would move into a new facility in August 2017.

   

Feasibility study meetings were held during Spring 2011. Wayside's modernization plan was approved by the Board of Education in August 2013.

Schematic Design Meetings:

The schematic design for Wayside's scheduled modernization was reviewed and discussed during the following meetings:

  • Wednesday, March 13, 2013: 3:45 pm
  • Thursday, April 4, 2013:  7:00 pm
  • Wednesday, April 17, 2013: 3:45 pm
  • Wednesday, May 1, 2013: 7:00 pm

All of the above meetings were held in Room 101, the Staff Development room in the addition.

The schematic design was presented at the PTA's General Membership meeting on Tuesday, May 7, 2013, at 7:00 pm in the All Purpose Room.

Minutes:

Schematic Design Kick-Off Meeting: Feb. 19, 2013

Schematic Design Meeting: March 13, 2013

Schematic Design Meeting: April 4, 2013

Schematic Design Meeting: April 17, 2013

Schematic Design Meeting (Staff): May 1, 2013

Schematic Design Meeting - Community, 7 pm:  May 1, 2013

 

Feasibility Study

Capacity and Feasibility Study: October 2011

Minutes from the Feasibility Meetings:

Holding Facility

Grosvenor Center

5701 Grosvenor Lane, Bethesda 20814

For additional information about MCPS Capital Improvement Projects, please use the following web links:

MCPS Division of Construction

MCPS Division of Long Range Planning

Capital Improvements Master Plan (please see the PDFs for the Winston Churchill Cluster Schools)