Modernization Updates and Information

Revised Site Plan approved by Board of Education on April 14, 2009

Modernization

What can you do? 4.16.09

Review Preliminary Plans Brochure presented to the Board of Education
Review plans

Support the Garrett Park ES Education Foundation
Learn more

Project Information and Updates

Construction BulletBOE accepted Preliminary Plans 4.14.09
Watch GPES presentation at Board of Ed meeting on April 14 
(GPES starts around 4:57)
Construction BulletACCEPTED Site Plan 4.01.09
Learn more (large file)
Construction BulletRevised Site Plan 3.18.19
Learn more
Construction BulletRevised Modernization Educational Specifications
For your review

Construction BulletAddition masterplan 2003
Take a closer look 

 

GPES Design and Construction Schedule

  • April 14 Presention to Board of Education
  • June 2009 Design development continues and construction documents are prepared
  • November 2009 Construction Documents are prepared
  • April 2010 Bid project
  • June 2010 Award project
  • June 2010 Move to holding school - Grosvenor ES
  • July 2010 Begin construction
  • January 2012 New school opens

Count down to construction ... 2010! 5 months!

 