Revised Site Plan approved by Board of Education on April 14, 2009

What can you do? 4.16.09
Review Preliminary Plans Brochure presented to the Board of Education Review plans
Support the Garrett Park ES Education Foundation Learn more
Project Information and Updates
BOE accepted Preliminary Plans 4.14.09 Watch GPES presentation at Board of Ed meeting on April 14
(GPES starts around 4:57)
ACCEPTED Site Plan 4.01.09 Learn more (large file)
Revised Site Plan 3.18.19 Learn more
Revised Modernization Educational Specifications For your review
Addition masterplan 2003 Take a closer look
|
GPES Design and Construction Schedule
- April 14 Presention to Board of Education
- June 2009 Design development continues and construction documents are prepared
- November 2009 Construction Documents are prepared
- April 2010 Bid project
- June 2010 Award project
- June 2010 Move to holding school - Grosvenor ES
- July 2010 Begin construction
- January 2012 New school opens
Count down to construction ... 2010! 5 months!
|