IAQ Team Building Maintenance Plan (BMP) Visit Progress - Waters Landing ES (109) Initial Visit
Kick-Off Meeting: 05/30/07
Walkthrough: 06/12/07
Work Plan Provided to School: 07/23/07 - Download
Supply Ventilation Unit PM (Cleaning; Mechanical Evaluation; Repairs, if needed):
Unit ID |
Area/Zone served by Unit |
Unit Type* |
Cleaned |
Mech Eval |
Repairs |
| 109-RTU4-MainOffice |
Main office suite |
RTU |
|
|
|
| 109-HU/StaffWkRm-A-1 |
Hall by main office workroom |
Fan Coil Unit |
09/26Q |
|
|
| 109-Health-D-1 |
Health room |
Heat Pump |
|
|
|
| 109-AsstPrin-D-1 |
Assistant Principal's office |
Heat Pump |
|
|
|
| 109-Prin-A-1 |
Principal's office |
Heat Pump |
|
|
|
| 109-Prin-D-1 |
Principal's office |
Heat Pump |
|
|
|
| 109-Con-A-1 |
Main office conference room |
Heat Pump |
|
|
|
| 109-CopyRm-A-1 |
Main office copy room |
Heat Pump |
|
|
|
| 109-Con2-A-1 |
Main office large conference room |
Heat Pump |
|
|
|
| 109-HU/MainEnt-B-1 |
Main entrance vestibule |
Fan Coil Unit |
09/28S |
|
|
| 109-K1-D-1 |
K1 |
Unit Ventilator |
10/02T |
|
|
| 109-HU/K1-B-1 |
K1, K2 vestibule |
Fan Coil Unit |
09/28Q |
|
|
| 109-K2-D-1 |
K2 |
Unit Ventilator |
10/03K |
|
|
| 109-K3-D-1 |
K3 |
Unit Ventilator |
10/02Q |
|
|
| 109-HU/K3-C-1 |
K3 vestibule |
Fan Coil Unit |
09/28K |
|
|
| 109-HU/K3-E-1 |
Hall by K3 |
Ceiling Fan Coil Unit |
09/28Q |
|
|
| 109-K4-D-1 |
K4 |
Unit Ventilator |
10/02K |
|
|
| 109-HU/K4-C-1 |
K4 vestibule |
Fan Coil Unit |
09/28K |
|
|
| 109-HU/Stair1-B-1 |
Stairwell by main entrance |
Fan Coil Unit |
09/28S |
|
|
| 109-Music-A-1 |
Music room |
Unit Ventilator |
10/03T |
|
|
| 109-HU/Music-CEF1 |
Student restrooms across main office |
CEF |
|
|
|
| 109-DPRm-A-1 |
Dual Purpose room |
Unit Ventilator |
10/03Q |
|
|
| 109-Art-A-1 |
Art room |
Unit Ventilator |
10/03S |
|
|
| 109-1-A-1 |
Room 1 |
Unit Ventilator |
10/03J |
|
|
| 109-HU/1-B-1 |
Hall front entrance by room 1 |
Fan Coil Unit |
09/26Q |
|
|
| 109-2-A-1 |
Room 2 |
Unit Ventilator |
10/03L |
|
|
| 109-HU/2-CEF2 |
Student restrooms across IMC |
CEF |
|
|
|
| 109-3-A-1 |
Room 3 |
Unit Ventilator |
10/04T |
|
|
| 109-4-A-1 |
Room 4 |
Unit Ventilator |
10/04Q |
|
|
| 109-5-A-1 |
Room 5 |
Unit Ventilator |
10/05T |
|
|
| 109-HU/5-E-1 |
Hall entrance by room 5 |
Ceiling Fan Coil Unit |
09/26S |
|
|
| 109-HU/Stair3-A-1 |
Hall stairwell by room 5 |
Fan Coil Unit |
09/26SK |
|
|
| 109-MechRm2-AHU |
Gym (heating and ventilation only) |
AHU |
|
|
|
| 109-HU/Gym-A-1 |
Gym outside entrance |
Fan Coil Unit |
09/26K |
|
|
| 109-ElevatorRm-C-1 |
Elevator mechanical room |
Fan Coil Unit |
|
|
|
| 109-Band-E-1 |
Band room |
SSAC |
|
|
|
| 109-StaffLounge-C-1 |
Staff lounge (first floor) |
Unit Ventilator |
|
|
|
| 109-6-C-1 |
Room 6 |
Heat Pump |
10/05Q |
|
|
| 109-7-C-1 |
Room 7 |
Heat Pump |
10/10LJ |
|
|
| 109-8-C-1 |
Room 8 |
Heat Pump |
10/12K |
|
|
| 109-9-C-1 |
Room 9 |
Heat Pump |
10/10LJ |
|
|
| 109-10-C-1 |
Room 10 |
Heat Pump |
10/11LJ |
|
|
| 109-HU/10-E-1 |
Hall by room 10 |
Ceiling Fan Coil Unit |
|
|
|
| 109-HU/Stair4-C-1 |
Stairwell by room 10 |
Fan Coil Unit |
|
|
|
| 109-RTU5-MPR |
Multipurpose Room |
RTU |
|
|
|
| 109-MPR-C-1 |
Multipurpose Room |
Baseboard Heater |
|
|
|
| 109-Stage-C-1 |
MPR stage |
Fan Coil Unit |
|
|
|
| 109-BoilerRm-E-1 |
Boiler room |
Ceiling Heater |
|
|
|
| 109-RTU2-Kitchen |
Kitchen, staff dining |
RTU |
|
|
|
| 109-SPT-D-1 |
Speech room |
Heat Pump |
10/11LJ |
|
|
| 109-2A-D-1 |
Room 2A |
Heat Pump |
|
|
|
| 109-2B-D-1 |
Room 2B |
Heat Pump |
|
|
|
| 109-11-A-1 |
Room 11 |
Unit Ventilator |
|
|
|
| 109-12-C-1 |
Room 12 |
Fan Coil Unit |
|
|
|
| 109-GBR/12-C-1 |
Girls' restroom by room 12 |
Fin-Tube Heater |
|
|
|
| 109-BBR/12-C-1 |
Boys' restroom by room 12 |
Fin-Tube Heater |
|
|
|
| 109-SBR/12-A-1 |
Staff restroom by room 12 |
Fin-Tube Heater |
|
|
|
| 109-HU/12-CEF5 |
Restrooms by room 12 |
CEF |
|
|
|
| 109-Storage206-A-1 |
Storage room 206 by room 12 |
Fin-Tube Heater |
|
|
|
| 109-12-CEF4 |
Restrooms by room 12 |
CEF |
|
|
|
| 109-13-A-1 |
Room 13 |
Unit Ventilator |
|
|
|
| 109-14-C-1 |
Room 14 |
Fan Coil Unit |
|
|
|
| 109-15-A-1 |
Room 15 |
Unit Ventilator |
|
|
|
| 109-16-C-1 |
Room 16 |
Fan Coil Unit |
|
|
|
| 109-17-A-1 |
Room 17 |
Unit Ventilator |
|
|
|
| 109-18-A-1 |
Room 18 |
Unit Ventilator |
|
|
|
| 109-19-A-1 |
Room 19 |
Unit Ventilator |
|
|
|
| 109-20-A-1 |
Room 20 |
Unit Ventilator |
|
|
|
| 109-21-A-1 |
Room 21 |
Unit Ventilator |
|
|
|
| 109-HU/21-B-1 |
Hall by room 21 |
Fin-Tube Heater |
|
|
|
| 109-Storage225-D-1 |
Storage room 225 across room 21 |
Fin-Tube Heater |
|
|
|
| 109-22-C-1 |
Room 22 |
Heat Pump |
|
|
|
| 109-23-C-1 |
Room 23 |
Heat Pump |
|
|
|
| 109-24-C-1 |
Room 24 |
Heat Pump |
10/12J |
|
|
| 109-25-C-1 |
Room 25 |
Heat Pump |
10/12T |
|
|
| 109-26-C-1 |
Room 26 |
Heat Pump |
10/12Q |
|
|
| 109-HU/26-B-1 |
Hall by room 26 |
Fin-Tube Heater |
|
|
|
| 109-Storage249-C-1 |
Storage room 249 across room 26 |
Fin-Tube Heater |
|
|
|
| 109-RTU1 |
Second floor rooms |
RTU |
|
|
|
| 109-RTU3-IMC |
IMC |
RTU |
|
|
|
* AHU: central air handling unit; Ceiling Unit Ventilator: ceiling-mounted ventilation unit; Unit Ventilator: wall-mounted ventilation unit; Ceiling Fan Coil Unit: ceiling-mounted ventilation unit (does not supply outdoor air); Fan Coil Unit: wall-mounted ventilation unit (does not supply outdoor air); RTU: rooftop air handler; VAV box: variable-air volume box (duct-mounted device that controls room temperatures by modulating airflow); Reheat Coil: duct-mounted device that provides supplemental heat. VAV boxes and reheat coils typically do not require cleaning; Heat Pump: Heat pump or refrigerant air-conditioner with electric heat; SSAC: split-system air-conditioner; Fin-Tube Heater: hydronic radiant heater (no fans); CEF: cabinet exhaust fan (provides make-up air for exhaust fans). |
Exhaust Fan PM (Mechanical Evaluation; Repairs, if needed):
Fan No. |
Area/Zone served by Unit |
Unit Type |
Mech Eval |
Repairs |
| |
|
|
|
|
| |
|
|
|
|
| |
|
|
|
|
| |
|
|
|
|
| |
|
|
|
|
| |
|
|
|
|
| |
|
|
|
|
| |
|
|
|
|
| |
|
|
|
|
| |
|
|
|
|
| |
|
|
|
|
| |
|
|
|
|
| |
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
Air Station PM:
Follow-Up Walkthrough:
Exit Meeting (Presentation of Site Visit Report and Building Maintenance Plan):
| Notes: |
| Recommended replacement of water-damaged, mold-contaminated pipe insulation in ceilings of rooms 2, 3, 4, and 5; |
| replacement of carpet in the music room; and installation of an exhaust fan for the main office copy room to Environmental Safety |
| Coordinator Yarup. |
| Visit suspended pending completion of HVAC energy management contractor project (08/09). Work resumed (09/26). |
| |
|
|